The assignments stated in this part are getting managed by County General public Will work staff members through contractors. For a lot more info, you should email [email protected], get in touch with 505.662.8150, or visit the “Projects/Public Works” connection at www.losalamosnm.us.

Make sure you gradual down and use caution in the design do the job zones. You should notice the underneath facts is dependent on a timetable supplied by the contractors and may well change due to weather conditions or other delays.  

Canyon Rim Path Underpass 

The recent highway detour will be shifted to the north aspect of NM502 allowing the contractor to work on the south aspect of the highway installing precast concrete packing containers and retaining partitions.   

Due to the total of construction exercise that incorporates trenching, excavation and utility relocation in the vicinity of the trailhead, the trailhead parking great deal, and a 100 ft. part of the trail near the trailhead remain closed for protection. AUI is hauling surplus content from project web page to a web page off DP Street. Motorists, bicyclists, and pedestrians are advised to continue to be notify for design personnel and machines and use warning touring by way of the perform zone. 

North Mesa Roadway and Utilities Advancement Job (Casa de Oro)

TLC Plumbing and Utility proceeds road and utility advancements on Alamo Rd, Capulin Rd, Tsankawi St, Oro Ct, Tsankawi Ct, Cedro Ct, and Huge Rock Loop South. The contractor will go on eliminating and replacing concrete sidewalks, driveway aprons and suppress and gutter in selected places alongside Capulin Rd, and Alamo Rd. Utility function will keep on on Capulin Rd and Tsankawi St including new h2o and gasoline main traces. Work several hours are 7 a.m. to 5 p.m., Monday via Friday, temperature allowing.  

Site visitors signals and devices will shift vehicular, bicycle, and pedestrian site visitors all over work zones. Accessibility to residents as properly as services these kinds of as mail shipping and delivery, crisis providers, university bus routes, trash and recycling selection will be taken care of. Motorists, bicyclists, and pedestrians are suggested to be warn for design staff and machines and use caution traveling through the get the job done zone.

Canyon Rim Strolling Trail

GME Emulsion, LLC continues trail rehabilitation on Canyon Rim Strolling Path from Knecht St. to the trail termini at the parking good deal at this time beneath design with the underpass. The 1st part of trail maintenance will be among Knecht St and DP road and 2nd segment is from DP Highway to the trail termini. These sections of the path will be shut in the course of the repairs which involve mill and overlay, crack sealing, and fog seal.

No road closure will happen throughout the development.  Do the job hrs are 7 a.m. to 5 p.m. Monday via Saturday, temperature permitting.

Leisure Lagoon (addition to the Aquatic Ctr.)

The bike lane alongside Canyon Road adjacent to the development area stays shut pending repaving. Bicyclists are encouraged to experience in the driving lane as the materials in the bicycle lane is smooth. The sidewalk is also shut in this spot, but pedestrians can wander in the bicycle lane spot in between the site visitors command devices and development fence.

Site visitors & Streets Division Tasks: 

The projects mentioned in this portion are remaining managed by County Website traffic & Streets Division employees. Be sure to sluggish down and use caution within the construction get the job done zones.

Countywide Clearing of Faculty Trails and Paths

In preparing for college to start Aug. 12, crews will be clearing school trails and paths beginning Monday and continuing until eventually comprehensive. Get the job done hours are every day from 7:30 a.m. to 3:30 p.m.

39th Road Sidewalk Repairs

Crews will be repairing sections of sidewalk together the east facet of 39th St. among Canyon Rd and Gold Road. The sidewalk will be closed.  There will also be some curb and asphalt restore that will effect targeted visitors. Flagging operations will be in spot as necessary. Development function will commence on Monday and continue on by means of Thursday 7:30 a.m. to 3:30 p.m.

University Zone Cleaning and Striping

In planning for faculty to begin Aug. 12, crews will be cleaning and striping college zones all over the County starting off Monday and continuing until eventually done. Crews will get started at 7:30 a.m. and conclude by 3 p.m. day by day. Flagging functions will be in location as needed.

Non-County Assignments:

The subsequent highway building updates are posted down below in the desire of maintaining inhabitants informed, but are staying managed or executed by others. You should obey all traffic products and gradual down in work zones.

Los Alamos Canyon Bridge Repairs (LANL):

Work proceeds on the west side of the bridge. Pedestrian/bicycle obtain is Closed Monday – Friday from 6 a.m. to 4 p.m. limitations are being taken off for entry during off-development several hours but pedestrians and bicyclists really should use caution if applying the pathway. The estimated duration for work to be finished on the west facet of the bridge is 3-4 months, and the all round undertaking is scheduled to acquire 6-8 months, temperature and plan dependent.

To prevent congestion and delays, consider making use of Atomic Metropolis Transit as a bus solution to cross the bridge. Look at out the Route 1 (downtown circulator bus) plan in this article.

Motorists are reminded to sluggish down in the construction location the velocity limit is 15 mph. Permit extra time for your commute in the course of peak travel occasions in the morning and night.

Anchor Ranch Rd Milling & Paving (LANL)

Crews keep on milling and paving Anchor Ranch Highway from Drop Road to WETF Highway.

West Jemez Rd – Eastbound (LANL)

For motorists utilizing eastbound West Jemez, remember to take note that the appropriate convert lane on to Diamond is nonetheless closed right up until Aug. 6. Motorists can however transform onto Diamond.

DP Rd (Work relevant to Canyon Walk Apts and The Bluffs – Bethel Progress)
Qualcon Builders, LLC – 120 DP Rd Utility Infrastructure Substitute and Roadway Reconstruction

Roadway reconstruction actions proceed with concrete collars and sidewalk design. These activities will effects DP Rd from Trinity Generate to Hearth Station #2 with segments of the roadway restricted to a single-lane website traffic managed by a flagged/signaled system. A person-lane traffic constraints will manifest only through hours of development most likely 7 a.m. to 7 p.m. each day.

The contractor work in DP Road is linked to the new Canyon Stroll Residences (beneath development) and The Bluffs senior housing (quickly to be produced). The roadway reconstruction involves set up of control and gutter, sidewalks and paving of the roadway. All construction functions linked to the reconstruction of DP Street will continue on all through the thirty day period of August.